Arcondec editorial · 23 / 11 / 2026
Data centres: 1,730 MW of demand by 2031

Mexico has 279 MW of installed data centre capacity and 205 MW under construction; demand could reach 1,730 MW by 2031. What it means for power engineering.
On 17 November 2026, Infobae reported, based on a Bloomberg story and data from the Mexican Data Center Association (MEXDC), that Mexico has 279 MW of installed data centre capacity and 205 MW under construction. Some 205 MW are expected by the end of 2026 and a similar amount in the first quarter of 2027, against projected demand of 1,730 MW in 2031. The report says connecting a project to the grid takes at least eight months and can take up to three years, while customers expect finished projects within 12 to 14 months.
What does going from 279 MW to 1,730 MW mean?
It means growing capacity more than sixfold in five years, according to the source’s figures. For engineering, the key figure is not only the total: the 410 MW expected between late 2026 and the first quarter of 2027 must be energised, tested and brought into operation within a few months, with substations, medium-voltage transformers and backup systems ready at the same time.
Grupo Arcondec services
The grid connection is the project’s critical path
If a grid connection can take between eight months and three years and the customer expects the building within 12 to 14 months, power engineering has to start before construction. In Arcondec’s view, feasibility, substation design and the procurement of medium-voltage transformers and switchgear are settled at the planning stage, not once the shell is already standing.
410 MW in six months demands rigorous commissioning
Energising two 205 MW blocks in such a short time concentrates equipment testing, protection coordination and integrated systems testing into the same period. Levelled commissioning, from individual equipment up to a loaded utility-failure test, reduces the risk that the first real event happens with customers already live.
Operating from day one with mission-critical discipline
Every megawatt that goes live needs predictive maintenance, thermography, battery and generator testing, and a 24/7 on-call team. For Arcondec, the O&M plan is designed alongside the EPC project so that the availability committed in the design is sustained throughout the site’s service life.
Data centre capacity in Mexico: installed, under construction and projected
| Indicator | Capacity | Horizon |
|---|---|---|
| Installed capacity | 279 MW | November 2026 |
| Capacity under construction | 205 MW | End of 2026 |
| Additional block expected | 205 MW (similar) | First quarter of 2027 |
| Projected demand | 1,730 MW | 2031 |
| Remaining after both blocks | 1,320 MW | 2027-2031 |
Source: Infobae, 17 November 2026, with data from the Mexican Data Center Association (MEXDC) and a Bloomberg report. The 1,730 MW projection comes from a DCD Intelligence and IDC study for MEXDC. These are industry figures, not Arcondec measurements.
Technical questions
How much data centre capacity is expected in Mexico by 2031?
Projected demand is 1,730 MW in 2031, according to a DCD Intelligence and IDC study for MEXDC cited by Infobae. The installed base is 279 MW and 205 MW are under construction. After the two 205 MW blocks expected between late 2026 and the first quarter of 2027, 1,320 MW would remain to be developed.
How long does it take to connect a data centre to the grid in Mexico?
At least eight months under normal conditions and up to three years in some cases, according to investors cited by Infobae. That is why power feasibility, substation engineering and medium-voltage equipment procurement should start at the planning stage, in parallel with the building design.
Which electrical equipment usually sets a data centre’s critical path?
Power and medium-voltage transformers, medium-voltage switchgear and standby generators are usually the longest-lead items. Defining their specifications early allows purchase orders to be placed on time and prevents energisation of the site from depending on whichever piece of equipment happens to arrive last.
What tests should be carried out before a data centre goes live?
Levelled commissioning: factory acceptance, site tests of each piece of equipment, system start-up, functional tests and an integrated test that simulates a utility failure under load. The integrated test confirms that UPS, transfer switches and generators respond as designed before customers move in.
Source / access date: 2026-11-17